Skip to content
BRENT 104.25 +17.25%
EUR/USD 1.16040 +0.50%
FRO 48.40 +25.88%
STNG 84.51 +10.56%
SBLK 30.74 +8.16%
ZIM 29.47 +16.90%
Tide Signal
Newsletter

Laytime Calculation in Shipping: Worked Time Sheet, Demurrage and Despatch Example

Laytime calculation turns the charterparty and Statement of Facts into a time account: when laytime starts, which periods count, which periods are excluded, when allowed time expires and whether demurrage or despatch is due. This guide works through a complete loading-port example from valid NOR to final time sheet, including weather stoppages, shifting, time on demurrage and the documentary checks operators should make before submitting or defending a claim.

Laytime calculation in shipping with bulk carrier cargo operations, Statement of Facts and demurrage time sheet
Bulk cargo operations alongside a worked laytime time sheet, showing how NOR, Statement of Facts, exceptions and cargo completion feed into demurrage or despatch.

Laytime calculation is where the charterparty and the port record meet. The calculation is not simply a subtraction of hours. The operator must first identify a valid Notice of Readiness, establish when the contractual clock starts, calculate the allowed time, classify every relevant event in the Statement of Facts and then determine whether time remains, demurrage has accrued or despatch is due.

96 hours Allowed laytime 48,000 mt at 12,000 mt per weather working day in the worked example.
116.5 hours Time counted After applying the specific exclusions stated in the example fixture.
20.5 hours Time on demurrage The amount by which counted time exceeds the allowed laytime.
$15,375 Demurrage due At an illustrative rate of $18,000 per day, pro rata.

A Statement of Facts records what happened. It does not decide whether the time counts. The charterparty performs that second job. “Rain stopped loading 0200–0530” is a fact; whether those 3.5 hours are deductible from laytime depends on the agreed laytime wording and the circumstances in which the interruption occurred.

What Is Laytime Calculation in Shipping?

Laytime calculation determines how much of the contractual time allowed for loading or discharging has been used. Once the allowed time is exhausted, further qualifying delay normally moves into demurrage. If cargo operations finish with time still available, despatch may be payable if the charterparty provides for it.

BIMCO’s Laytime Definitions for Charter Parties 2013 define laytime as the agreed period during which the owner makes and keeps the vessel available for loading or discharging without additional payment beyond freight. They separately define Notice of Readiness, demurrage, despatch, weather working days, reversible laytime and other expressions that can change the result of a time sheet.

For the wider commercial framework, Tide Signal’s Types of Charter Parties in Shipping explains why laytime and demurrage are primarily voyage-charter mechanisms, while time charters operate mainly through hire and off-hire.

1. ArrivalIs the vessel an arrived ship under the fixture?
2. NORWas a valid NOR tendered correctly?
3. StartWhen does laytime commence?
4. CountWhich SOF periods count or stop?
5. ResultTime saved, laytime remaining or demurrage?

What You Need Before Starting a Laytime Calculation

A reliable laytime calculation should not be built from memory or from a single email. The operator normally works from a document pack and the actual charterparty wording.

Fixture recap and charterpartyLaytime rate, NOR rules, exceptions, demurrage, despatch and rider clauses.
Notice of ReadinessDate, time, place, method of tender and evidence of receipt.
Statement of FactsChronological port events and cargo-operation times.
Port log / agent recordsUseful support for movements, berth availability and local events.
Weather recordsNeeded where weather exceptions are relied upon.
Letters of ProtestImportant where facts, delays or signatures are disputed.
Cargo documentsBill of lading quantity and cargo completion times where relevant.
Claim time-bar clauseDeadline and documentary requirements for the final claim.

The documentary point is not administrative detail. Steamship Mutual’s discussion of demurrage time bars notes that charterparties may require NORs, SOFs, port logs, time sheets, letters of protest and other supporting records, and that failure to provide the contractually required package can defeat an otherwise valid claim. See its Demurrage Time Bars FAQs.

The Laytime Calculation Sequence: From Charterparty to Final Time Sheet

A professional laytime calculation is easier to audit when it follows a fixed order. Good operators calculate in a fixed order. Jumping straight to rain deductions or demurrage before confirming commencement is one of the easiest ways to produce a polished but wrong time sheet.

  1. Read the recap and governing charterparty. Identify the exact laytime wording and any riders that amend the printed form.
  2. Establish the allowed laytime. It may be stated as a number of days/hours or derived from a cargo rate.
  3. Check the vessel’s arrival and NOR. Confirm place, readiness, timing and method of tender.
  4. Apply notice time or commencement wording. Six hours after NOR, next working day, 1400 hours, “unless sooner commenced” or another agreed trigger.
  5. Build a chronological time sheet from the SOF. Do not classify an event before checking the clause that governs it.
  6. Apply exclusions and inclusions. Weather, Sundays/holidays, shifting, breakdowns and waiting periods are clause-dependent.
  7. Identify the exact moment allowed laytime expires. This is the transition point into demurrage.
  8. Apply the demurrage or despatch rate. Usually per day or pro rata, as stated in the fixture.
  9. Check the supporting documents and time bar. A correct number still needs a contract-compliant claim package.

How to Calculate Allowed Laytime

Sometimes the charterparty gives a fixed allowance, for example “4 weather working days of 24 consecutive hours”. In other fixtures, allowed laytime is derived from the cargo quantity and an agreed loading or discharging rate.

Allowed Laytime (days) = Cargo Quantity ÷ Agreed Cargo Rate per Day

In the worked example:

48,000 mt ÷ 12,000 mt/day = 4.00 days = 96 hours

That looks simple, but the cargo basis itself may need checking. The relevant quantity might be the bill of lading quantity, the nominated quantity or another contractual basis. Short-loading clauses can also affect the calculation.

BIMCO’s GENCON 2022 provides for laytime to be expressed as running days or a cargo rate and incorporates the BIMCO Laytime Definitions 2013 except where inconsistent with the charterparty terms.

When Does Laytime Start?

This is usually the most important question in the calculation. A five-hour error at commencement can become a five-hour error in demurrage.

Most voyage charterparties make commencement conditional on a valid Notice of Readiness. Gard notes that, where a valid NOR is required, an invalid notice may prevent laytime from commencing unless the circumstances support waiver or another contractual route to commencement. See Gard’s analysis of Notice of Readiness and the commencement of laytime.

Tide Signal’s detailed Notice of Readiness in Shipping guide covers arrived-ship status, physical readiness, legal readiness and the distinction between tendering NOR and the later commencement of laytime.

Turn time and “unless sooner commenced”

Assume the fixture says laytime begins six hours after valid NOR, unless sooner commenced. If NOR is validly tendered at 0900, the normal start would be 1500. If cargo operations actually begin at 1330, the “unless sooner commenced” wording can bring forward commencement to 1330 under the BIMCO definition, subject to the wording incorporated into the actual contract.

NOR tendered is not automatically laytime started. The time sheet needs two separate entries: the valid NOR time and the contractual commencement time.

Do not confuse this with laycan. Laycan defines the agreed arrival/cancelling window. Laytime concerns the time allowed for cargo operations after the relevant contractual trigger.

How to Read the Statement of Facts

The SOF is the factual backbone of the time sheet. It should tell the reader when the vessel arrived, tendered NOR, entered port, anchored, berthed, shifted, started cargo, stopped cargo, resumed cargo, completed operations and sailed, together with relevant weather or operational interruptions.

But the SOF should remain a record of events. It should not silently decide the legal effect of those events.

SOF says“Rain stopped loading 0200–0530.”
Charterparty asksDoes bad weather suspend laytime under this wording?
Time sheet decidesCount, exclude or treat differently based on the contract.

This separation matters in disputes. Steamship Mutual’s discussion of The Ocean Neptune shows how documentary requirements around SOFs and other supporting records can become central to whether a demurrage claim survives a contractual time bar.

How Weather, SHEX and SHINC Change a Laytime Calculation

In any laytime calculation, there is no universal rule that every stoppage shown in an SOF is deducted from laytime. The charterparty wording governs.

Weather working days

Under BIMCO’s definition of a Weather Working Day of 24 Consecutive Hours, the actual period during which weather interrupts or would have interrupted cargo work is excluded from laytime. Other weather-working formulations can produce different calculations, so the exact words matter.

SHINC and SHEX

SHINC generally means Sundays and holidays are included in laytime. SHEX means the specified Sundays and holidays are excluded, subject to the wording and any qualifier such as “unless used”. The difference can move the expiry of laytime by a full weekend or holiday period.

Shifting

Whether shifting counts depends on the fixture. GENCON 2022 contains specific provisions for shifting in the circumstances it addresses, but rider clauses can alter the position. A time sheet should therefore state the contractual reason for excluding or counting a shift rather than simply marking “shifting — deductible”.

Breakdowns and cargo availability

A shore conveyor breakdown, shortage of trucks or cargo unavailability does not automatically stop laytime. If the charterparty contains no applicable exception, the time may continue to count. Conversely, delay caused by the vessel or an owner-side breach can have a different result.

The event tells you what happened. The clause tells you who carries the time.

Worked Laytime Calculation: Full Time Sheet Example

The following example is deliberately specific. It is not intended to state a universal rule for every voyage charter.

Fixture itemWorked assumption
Cargo48,000 mt
Loading rate12,000 mt per weather working day of 24 consecutive hours
Allowed laytime4 days / 96 hours
NORValidly tendered Monday 0900
Commencement6 hours after valid NOR, unless sooner commenced
Cargo startsMonday 1330, therefore laytime starts at 1330 for this example
WeatherWeather interruption excluded while laytime is running
ShiftingOne specific 2-hour shift excluded by the hypothetical rider clause
Demurrage$18,000/day, pro rata
Demurrage exceptionsNo separate weather exception once on demurrage in this hypothetical fixture

Because cargo starts at 1330 — before the normal 1500 expiry of the six-hour notice period — the agreed “unless sooner commenced” wording brings the start of laytime forward to 1330 in this example.

Period / event Elapsed Treatment Laytime counted Running total
Mon 1330 → Tue 0200
Cargo operations / normal time
12.5 h Counts 12.5 h 12.5 h
Tue 0200 → 0530
Rain stops loading
3.5 h Excluded under the example weather wording 0 12.5 h
Tue 0530 → Wed 1100 29.5 h Counts 29.5 h 42.0 h
Wed 1100 → 1300
Shift between berths
2.0 h Excluded only because the hypothetical rider says so 0 42.0 h
Wed 1300 → Thu 1800 29.0 h Counts 29.0 h 71.0 h
Thu 1800 → 2200
Shore conveyor breakdown
4.0 h Counts: no applicable exception assumed 4.0 h 75.0 h
Thu 2200 → Fri 0700 9.0 h Counts 9.0 h 84.0 h
Fri 0700 → 1000
Awaiting cargo
3.0 h Counts 3.0 h 87.0 h
Fri 1000 → 1900 9.0 h Counts 9.0 h 96.0 h — laytime exhausted
Fri 1900 → Sat 0500 10.0 h Demurrage 10.0 h demurrage
Sat 0500 → 0700
Rain
2.0 h Still demurrage in this example: no express demurrage weather exception 12.0 h demurrage
Sat 0700 → 1530
Loading completed 1530
8.5 h Demurrage 20.5 h demurrage
Final result
96 hAllowed laytime
116.5 hTotal counted time
20.5 hExcess time
$15,375Demurrage due

The key operational moment is Friday 1900. That is when the 96 counted hours are exhausted after allowing for the 3.5-hour weather interruption and the 2-hour shift expressly excluded by the hypothetical fixture.

Laytime Calculation Result: How to Calculate Demurrage

Once the allowed laytime has been used, the excess qualifying time is multiplied by the contractual demurrage rate.

Demurrage = Excess Time ÷ 24 × Demurrage Rate per Day

For the example:

20.5 hours ÷ 24 × $18,000/day = $15,375

BIMCO’s Laytime Definitions describe demurrage as an agreed amount payable for delay once laytime has expired and state that laytime exceptions do not automatically apply to demurrage unless the charterparty specifically says they do.

This is the basis of the familiar principle discussed in shipping as “once on demurrage, always on demurrage”, although the actual charterparty and owner-caused delay can alter the result. Steamship Mutual’s discussion of the principle illustrates why it should not be applied mechanically without reading the agreed exceptions.

How Despatch Is Calculated

If cargo operations finish before allowed laytime is exhausted and the charterparty provides for despatch, the owner may owe the charterer an agreed amount for time saved.

BIMCO distinguishes between all working time saved and all time saved. The difference matters because excepted periods can be treated differently in the despatch calculation.

Assume, separately from the main example, that the charterparty provides despatch at half the demurrage rate on all time saved and the vessel finishes with seven hours of laytime remaining:

Despatch Rate = $18,000/day ÷ 2 = $9,000/day
7 hours ÷ 24 × $9,000/day = $2,625 despatch

For a fuller commercial explanation, use Tide Signal’s existing despatch guide alongside the actual fixture wording. The important point in any calculation is to identify whether the clause says all time saved, all working time saved or another basis.

Reversible, Non-Reversible and Averaged Laytime

Loading and discharging time cannot always be calculated in isolation. The charterparty may allow the charterer to combine or set off time between the two ends of the voyage.

StructureHow it worksCommercial effect
Non-reversible / separate Loading and discharging allowances are calculated independently. Time saved at one end does not automatically rescue excess time at the other.
Reversible laytime The charterer may combine the allowed loading and discharging time. Unused time at one end can be applied against time used at the other.
To average laytime Separate calculations are made, then time saved is set off against excess time used. The final economic result is netted between ports as the clause permits.

BIMCO defines both “to average laytime” and “reversible laytime” separately. That distinction is worth preserving because the words used in the fixture determine the calculation mechanics.

From a Time Sheet to a Demurrage Claim

A laytime calculation is not complete when the spreadsheet produces a dollar figure. The claim must also satisfy any contractual notice and documentation requirements.

Depending on the charterparty, a claim package may require:

  • owners’ laytime/demurrage calculation;
  • NOR at each relevant port;
  • signed Statement of Facts;
  • port log or terminal records;
  • letters of protest;
  • weather evidence;
  • cargo or pumping logs where relevant;
  • invoice and supporting correspondence;
  • submission within the specified contractual time bar.

The Ocean Neptune decision is a useful reminder that documentary compliance can be decisive. Steamship Mutual explains that the claim in that case was affected by failure to meet contractual supporting-document requirements.

The commercial lesson is straightforward: do not wait until day 89 of a 90-day time bar to discover that the terminal never countersigned the SOF.

Common Laytime Calculation Mistakes That Change the Claim

  1. Starting the clock at NOR tender rather than contractual commencement.
  2. Using an invalid NOR without considering the effect on commencement.
  3. Confusing laycan with laytime.
  4. Treating every SOF stoppage as an automatic deduction.
  5. Ignoring the exact weather-working-day formulation.
  6. Applying SHEX or SHINC from memory rather than the fixture wording.
  7. Deducting shifting time without a contractual basis.
  8. Continuing to apply ordinary laytime exceptions after demurrage has started when the clause does not permit it.
  9. Using the wrong cargo quantity to calculate allowed laytime.
  10. Forgetting whether laytime is reversible or averaged.
  11. Calculating the amount correctly but missing the claim time bar.
  12. Submitting an incomplete evidence package.
The most expensive laytime error is often not arithmetic. It is applying the right arithmetic to the wrong contractual assumption.

Operator’s Laytime Calculation Review Checklist

Fixture wordingHave all relevant recap and rider amendments been identified?
Allowed timeFixed days/hours or cargo-rate calculation?
Arrived shipWas the vessel in the required contractual place?
NORValid, factually accurate and tendered by an allowed method?
CommencementNotice time, office hours and “unless sooner commenced” checked?
SOFChronology complete and signatures/remarks reviewed?
WeatherExact weather wording and supporting evidence checked?
SHEX / SHINCSunday/holiday treatment confirmed from the contract?
ShiftingCount or exclude under the actual clause?
BreakdownsWhose sphere and what exception, if any, applies?
Demurrage startExact expiry moment of allowed laytime identified?
After demurrageDo any exceptions expressly continue?
DespatchAll time saved or all working time saved?
Time barDeadline and required documents diarised?

Port time also feeds directly into voyage economics. Tide Signal’s Voyage Estimation in Shipping guide shows why expected port duration affects TCE even before the contractual laytime claim is known. The Voyage Margin Calculator can then be used to test the commercial effect of additional voyage cost.

For a broader view of waiting time outside the pure laytime regime, Tide Signal’s homepage and Operations coverage also connect port delays with voyage margins, scheduling and cargo planning. See Tide Signal for the latest operational and chartering analysis.

Laytime Calculation: Frequently Asked Questions

What is the basic laytime calculation formula?

Where laytime is based on a cargo rate, allowed laytime is cargo quantity divided by the agreed loading or discharging rate. The resulting allowed time is then compared with counted time after applying the charterparty’s commencement rules and exceptions.

When does laytime start after NOR?

It depends on the charterparty. A valid NOR may be followed by six hours’ notice, a specified start time, office-hour provisions or wording such as “unless sooner commenced”. Tendering NOR and starting laytime are separate events.

Does rain always stop laytime?

No. Weather treatment depends on the agreed wording. A weather working day clause may exclude qualifying weather interruption, while running-day wording or a different clause can produce another result.

Does shifting time count as laytime?

It depends on the charterparty and the reason for the shift. The correct treatment must come from the applicable printed and rider clauses, not from a blanket rule.

What happens when allowed laytime expires?

Further qualifying delay normally moves into demurrage at the agreed rate. The exact treatment of later exceptions depends on the charterparty.

How is demurrage calculated?

Excess qualifying time is divided by 24 and multiplied by the agreed daily demurrage rate when the rate is expressed per day and pro rata.

What is despatch?

Despatch is an agreed amount payable by the owner when cargo operations finish before allowed laytime expires, if the charterparty provides for it. The basis may be all time saved, all working time saved or other wording.

What is the difference between SOF and a laytime time sheet?

The Statement of Facts records what happened and when. The laytime time sheet applies the charterparty to those facts and decides which periods count toward allowed time.

What is reversible laytime?

Reversible laytime allows the charterer to combine the time allowed for loading and discharging, subject to the agreed clause, rather than treating each end as completely separate.

Can a demurrage claim fail even if the calculation is correct?

Yes. A claim can be affected by contractual time bars, notice requirements or missing supporting documents. The actual charterparty determines what must be submitted and when.

References

This article explains general chartering and operational principles through a hypothetical worked example. The signed charterparty, incorporated terms, rider clauses, governing law and transaction-specific facts determine the actual laytime and demurrage result.

Email article